Progress Report Centrecare's new Midland Building in Yelverton Drive.

19 January 2015


15 Jan 2015 - Ground floor slab NW portion was poured; Formcraft wall formwork to children’s counselling room & bin room was erected. The last portion of the basement floor was poured. First floor east side Bubbledeck was installed and pouring is scheduled next week. Work to basement ramp starts today. Formwork to basement soffit & corbels will be stripped next week, basement lighting (electrical) & mechanical work to follow.